During the most recent month at Coggan Corporation, queue time was 5.3 days, inspection time was 0.5

Question:

During the most recent month at Coggan Corporation, queue time was 5.3 days, inspection time was 0.5 day, process time was 1.9 days, wait time was 4.5 days, and move time was 0.5 day.
Required: a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.