Elkland Heating & Cooling installs and services commercial heating and cooling systems. Elkland uses job costing to
Question:
___________________________________Job 101______Job 102
Direct materials used .................................... $15,000...........$10,000
Direct labor hours used ........................................ 155.....................72
Elkland paid a $24-per-hour wage rate to the employees who worked on these two jobs.
Requirements
1. What is Elkland's predetermined overhead rate based on direct labor hours?
2. Calculate the overhead to be allocated to each of the two jobs based on direct labor hours.
3. What is the total cost of Job 101? What is the total cost of Job 102?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: