Task___________ Predecessor_____________ Average Time (sec)
A..............................none............................................45
B..............................none............................................90
C................................A............................................110
D................................B............................................120
E..............................none...........................................100
F...............................C...............................................15
G...............................E.............................................115
H............................F, D, G..........................................35
The Plant Manager needs first shift to achieve an output of 100 cars.
Compute the Takt time for the line.
What is the theoretical minimum number of workstations?
Draw the precedence diagram. Then assign tasks to work stations and you must use the largest eligible task heuristic rule to break any ties. Show which tasks are assigned to each workstation.
Compute the efficiency and percent idle time for the system .
What is the maximum output that could be achieved by a single assembly line in 8 hours?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Accounting Business Reporting For Decision Making
ISBN: 9780730302414
4th Edition
Authors: Jacqueline Birt, Keryn Chalmers, Albie Brooks, Suzanne Byrne, Judy Oliver
Question Posted: