Five years ago a chemical plant invested $90,000 in a pumping station on a nearby river to
Question:
Maintenance....................$2,000 per year
Power and labor.................4,500 per year
Taxes and insurance.............1,000 per year
Total.............................$7,500 per year
A nearby city has offered to purchase the pumping station for $75,000 as it is in the process of developing a city water distribution system. The city is willing to sign a 10-year contract with the plant to provide the plant with its required volume of water for a price of $10,000 per year. Plant officials estimate that the salvage value of the pumping station 10 years hence will be about $30,000. The before-tax MARR is 10% per year. An effective income tax rate of 50% is to be assumed. Compare the annual cost (after taxes) of the defender (keep the pumping station) to the challenger (sell station to the city) and help plant management determine the more economical course of action.
Salvage Value
Salvage value is the estimated book value of an asset after depreciation is complete, based on what a company expects to receive in exchange for the asset at the end of its useful life. As such, an asset’s estimated salvage value is an important... MARR
Minimum Acceptable Rate of Return (MARR), or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other... Distribution
The word "distribution" has several meanings in the financial world, most of them pertaining to the payment of assets from a fund, account, or individual security to an investor or beneficiary. Retirement account distributions are among the most...
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Engineering Economy
ISBN: 978-0132554909
15th edition
Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Question Posted: