For the following test marketing project at week 6: a. Ignore the far right % Complete column
Question:
a. Ignore the far right % Complete column and using the 5050 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.
b. Repeat the calculations in a, but now using the % Complete column. Assume that the PV values are based on time proportionality but the % Complete values for EV are from the workers actually doing thetasks.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted: