For the following test marketing project at week 6: a. Ignore the far right % Complete column

Question:

For the following test marketing project at week 6:
a. Ignore the far right €œ% Complete€ column and using the 50€“50 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.
b. Repeat the calculations in a, but now using the €œ% Complete€ column. Assume that the PV values are based on time proportionality but the €œ% Complete€ values for EV are from the workers actually doing thetasks.