For the network shown: a. Determine the critical path and the early completion time in weeks for
Question:
For the network shown:
a. Determine the critical path and the early completion time in weeks for the project.
b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at yourschedule.