Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean:
Question:
a) How many weeks in advance of the film release should Four Squares has started its marketing campaign? What is the critical path? The tasks (in time units of weeks) are as follows:
b) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketingcampaign?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: