Given an auditing project with the following activities, Using the critical path, find: (a) The probability of

Question:

Given an auditing project with the following activities,


Given an auditing project with the following activities,  .:.


Using the critical path, find:
(a) The probability of completing this project in 12 weeks (or less), as the client desires.
(b) The probability of completing this project in 13 weeks (or less).
(c) The probability of completing this project in 16 weeks (or less), the client's drop-dead date.
(d) The number of weeks required to assure a 92.5 percent chance of completion, as guaranteed by the auditingfirm.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: