Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network

Question:

Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram.
(a) Which activities are on the critical path?
(b) What is the length of the criticalpath?