Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?

14 15 12 Lights 12 26 27 27 н 27 28 23 25 Lag 1 Paint 11 14 Open Lot Pave Parkin Prepare Site Post Lines Signs 27 28 23