Given the following production plan, use a (a) Chase production strategy (b) Level production strategy to compute

Question:

Given the following production plan, use a
(a) Chase production strategy
(b) Level production strategy to compute the monthly production, ending inventory / (backlog) and workforce levels. A worker can produce 50 units per month. Assume that the beginning inventory in January is 500 units, and the firm desires to have 200 of inventory at the end ofJune.