Given the information in the following table, draw the AOA network. Using the same information, enter the

Question:

Given the information in the following table, draw the AOA network. Using the same information, enter the data into MSP assuming a seven-day workweek. (To change the calendar in MSP from its five-day week default click "Help," type "calendar change," and follow directions.) Develop the appropriate AON network and Gantt chart. Using any method you wish, find the critical path and critical time for the network. Then find the slack for allactivities.

Given the information in the following table, draw the AOA
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management in Practice

ISBN: 978-0470533017

4th edition

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

Question Posted: