Gonzales, Inc., is preparing its direct labor budget for 2011 from the following production budget based on
Question:
Gonzales, Inc., is preparing its direct labor budget for 2011 from the following production budget based on a calendar year.
Quarter Units
1 ......... 20,000
2 ......... 25,000
3 ......... 35,000
4 ......... 30,000
Each unit requires 1.6 hours of direct labor.
Instructions
Prepare a direct labor budget for 2011. Wage rates are expected to be $15 for the first 2 quarters and $16 for quarters 3 and 4.