Question: A government agency has estimated that a flood control project has costs and benefits that are parabolic, according to the equation (Present worth of benefits)2
A government agency has estimated that a flood control project has costs and benefits that are parabolic, according to the equation (Present worth of benefits)2 - 22(Present worth of cost) + 44 = 0 where both benefits and costs are stated in millions of dollars. What is the present worth of cost for the optimal size project?
Step by Step Solution
3.37 Rating (169 Votes )
There are 3 Steps involved in it
The problem requires the student to use calculus The text poi... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
7-B-E-M (497).docx