Gramercy, Inc., manufactures sailboats and has two major categories of overhead: materials handling and quality inspection. The
Question:
Materials handling (based on 500 material moves) ..... $100,000
Quality inspection (based on 200 inspections) .......$300,000
The plant currently applies overhead based on direct labor hours. The estimated amount of direct labor hours is 50,000. Polly Richardson, the plant manager, has been asked to submit a bid and has assembled the following data on the proposed job:
Direct materials ........ $3,700
Direct labor (1,000 hours) ..... $17,000
Overhead .......... ?
Number of material moves .... 10
Number of inspections ..... 5
Polly has been told that many similar companies use an activity-based approach to assign overhead to jobs. Before submitting a bid, Polly wants to assess the effects of this alternative approach.
Required
A. Calculate the total cost of the potential job using traditional overhead application.
B. Calculate the total cost of the job using activity-based costing with the new cost drivers to allocate overhead.
C. Discuss the difference in the costs calculated under the two overhead allocation methods and what impact the change to activity-based costing might have on the pricing decision.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managerial Accounting A Focus on Ethical Decision Making
ISBN: 978-0324663853
5th edition
Authors: Steve Jackson, Roby Sawyers, Greg Jenkins
Question Posted: