Identify the term being described for each of the following:

a. A sequence of activities in a project.

b. The longest time sequence of activities in a project.

c. Used when two activities have the same starting and finishing points.

d. The difference in time length of any path and the critical path.

e. The statistical distribution used to describe variability of an activity time.

f. The statistical distribution used to describe path variability.

g. Shortening an activity by allocating additional resources.


Distribution
The word "distribution" has several meanings in the financial world, most of them pertaining to the payment of assets from a fund, account, or individual security to an investor or beneficiary. Retirement account distributions are among the most...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0078024108

12th edition

Authors: William J Stevenson

Question Posted: