Question: If 200 labor hours were required to produce the 15tunit in a production run and 60 labor hours were required to produce the 7th unit,

If 200 labor hours were required to produce the 15tunit in a production run and 60 labor hours were required to produce the 7th unit, what was the learning-curve rate during production?

Step by Step Solution

3.36 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

T 7 T1 x 7 b 60 200 x 7 b 0200 7 b Log 030 b log 7 b ... View full answer