If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180

Question:

If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so for how many days?

Crash Act. Maximum Normal Normal Cost Crash Time Time Cost (Slope) 80 10 40 10 30 3 40 80 D 50 2 11 50 100 4 15 100 30 1
A D 10 11 Project duration 27 Total direct cost $300 15 B. 00
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management The Managerial Process

ISBN: 978-1259666094

7th edition

Authors: Erik W. Larson, Clifford F. Gray

Question Posted: