Question: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

In 2018, the Westgate Construction Company entered into a contract

Westgate recognizes revenue over time according to percentage of completion.
Required:
1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.
2. Prepare all necessary journal entries for each of the years (credit "various accounts" for construction costs incurred).
3. Prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities.
4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:

In 2018, the Westgate Construction Company entered into a contract

5. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:

In 2018, the Westgate Construction Company entered into a contract

2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 2020 $2,200,000 4,000,000 4,600,000 2019 2018 $2,400,000 5,600,000 2020 Costs incurred during the year Estimated costs to complete as of year-end 31,3 3,100,000 3.800.000 $ 3,200,000 2019 $3,800,000 4,100,000 2020 2018 $2,400,000 5,600,000 $3,900,000 Costs incurred during the year Estimated costs to complete as of year-end

Step by Step Solution

3.47 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Requirement 1 2018 2019 2020 Contract price 10000000 10000000 10000000 Actual costs to date 2400000 6000000 8200000 Estimated costs to complete 5600000 2000000 0 Total estimated costs 8000000 8000000 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1265-B-C-A-C-B-A-M(2399).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!