Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards

Question:

Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards in each 8-hour card-making session. Figure details each work element and its associated durations in minutes as well as their precedence relationships.

a. What cycle time is required to satisfy the required output rate?

b. What is the theoretical minimum number of workstations required?

c. If lane identifies a five-station solution, what is the associated efficiency and balance delay?

Jane produces custom greeting cards using six distinct work elem


d. If the cycle time increased by 100 percent, would the theoretical minimum number of workstations also increase by 100 percent?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

Question Posted: