Judy's Cake Shop makes fresh cakes to customer orders. After receiving the order by Judy's assistant, which
Question:
a. What is the capacity of the process, and what is the bottleneck?
b. What is the throughput time for a typical cake?
c. If on average five orders are taken per hour, how many cakes are there in the process (on average)?