Kiner, Inc. began work in 2012 on a contract for $12,600,000. Other data are as follows: If

Question:

Kiner, Inc. began work in 2012 on a contract for $12,600,000. Other data are as follows:
2013 2012 Costs incurred to date $5,400,000 $8,400,000 Estimated costs to complete 3,600,000 Billings to date 4,200,000

If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2012 is: