Question: LO Ventures, LLC, doing business as Reef point Brew house in Racine, Wisconsin, contracted with Forman Awnings and Construction, LLC, for the fabrication and installation
LO Ventures, LLC, doing business as Reef point Brew house in Racine, Wisconsin, contracted with Forman Awnings and Construction, LLC, for the fabrication and installation of an awning system over an outdoor seating area. After the system was complete, Reef point expressed concerns about the workmanship but did not give Forman a chance to make repairs. The brew house used the awning for two months and then had it removed so that siding on the building could be replaced. The parties disagreed about whether cracked and broken welds observed after the removal of the system were due to shoddy workmanship. Reef point paid only $400 on the contract price of $8,161. Can Reef point rescind the contract and obtain a return of its $400? Is Forman entitled to recover the difference between Reef point's payment and the contract price? Discuss.
Step by Step Solution
3.34 Rating (160 Votes )
There are 3 Steps involved in it
Reef point cannot rescind the contract and obtain a return of its 400 nor Is Forman entitled to recover the difference between Reef points payment and ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1227-L-B-L-L-E(4597).docx
120 KBs Word File