Multiple Choice Questions
1. In the bottom-up approach to cost estimating:
(a) Required price is an input variable.
(b) Cost estimates are an output variable.
(c) Required price is an output variable.
(d) Both (a) and (b) are correct.
2. A ratio of the cost of something today to its cost at some time in the past is called a:
(a) Cost-capacity index
(b) Cost index
(c) Buyer’s guide
(d) Bluebook index
3. Index values could probably be obtained from all of the following places except:
(a) Trade organizations
(b) Engineering News Record magazine
(c) Government organizations
(d) Home Depot or Lowe’s home improvement stores
4. The equipment for applying specialty coatings that provide a high angle of skid for the paperboard and corrugated box industries has a delivered cost of $390,000. If the overall cost factor for the complete system is 2.96, the total plant cost is approximately:
(a) $954,400
(b) $1,054,400
(c) $1,154,400
(d) $1,544,400
5. A police department wants to allocate the indirect cost of speed monitoring to the three toll roads around the city. An allocation basis that may not be reasonable is:
(a) Miles of toll road monitored
(b) Average number of cars patrolling per hour
(c) Amount of car traffic per section of toll road
(d) Cost to operate a patrol car
6. If the engineering department is the activity to receive indirect cost allocation for the year, cost drivers for the ABC method that seem reasonable may be:
1. Cost of engineering changes processed
2. Size of the workforce
3. Administrative cost to process a change order
(a) 1
(b) 2
(c) 3
(d) 1 and 3
7. Advantages of the ABC method are:
1. It is an excellent replacement for a traditional cost accounting system.
2. It is always cheaper to operate than a traditional allocation system.
3. It can help explain the economic impact of management decisions.
(a) 1
(b) 2
(c) 3
(d) 1 and 3