Question: Old room and pillar workings extend under Hometown where the strata roll to the horizontal (depth = 1,750 ft, 533 m) and where additional protection

Old room and pillar workings extend under Hometown where the strata roll to the horizontal (depth = 1,750 ft, 533 m) and where additional protection in the form of river-run sand fill is placed hydraulically through boreholes. The extraction ratio in this area is estimated to be about 40%. Once in place, the fill is grouted for additional strength. Laboratory test data from 4-in. (10.2 cm) diameter samples, 4 in. (10.2 cm) long (not grouted) are given in Table 7.7. Estimate the hydraulic conductivity of the fill(in./h).

Table 7.7 Fill test data Time (min) Head (in.) (cm) 1.90 4.22

Table 7.7 Fill test data Time (min) Head (in.) (cm) 1.90 4.22 114 0.0 7.22 36.0 30.0 24.0 61.0 18.0 45.3 12.0 91.4 76.2 30.5 Note The standpipe inside diameter is 0.5 in. (1.27 cm).

Step by Step Solution

3.27 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Given Falling head permeameter data Find hydraulic conductivi... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

26-E-G-R (304).docx

120 KBs Word File

Students Have Also Explored These Related Geological Engineering Questions!