On average, the manufacturing (processing) time spent per order is approximately four days. In addition, a typical

Question:

On average, the manufacturing (processing) time spent per order is approximately four days. In addition, a typical order spends four days moving from process to process, three days in storage, and two days in inspection. For an average order, what is the manufacturing cycle efficiency?