On July 1, 2019, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp.

Question:

On July 1, 2019, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2021, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2019, 2020, and 2021.
At 12/31/19 At 12/31/20 At 12/31/21 $ 300,000 $1,200,000 $2,100,000 1,200,000 300,000 1,100,000 1,850,000 Contract costs

Instructions
a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, and 2021. (Ignore income taxes.)
b. Using the cost-recovery method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, and 2021. (Ignore income taxes.)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting IFRS

ISBN: 978-1119372936

3rd edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: