Plum Electronics, a division of Berry Corporation, manufactures two large-screen television models: the Mammoth, which has been
Question:
Plum Electronics Income Statement for the Fiscal Year Ended November 30, 2013
Details for cost of goods sold for Mammoth and Maximum are as follows.
aMammoth requires 1.5 hours per unit and Maximum requires 3.5 hours per unit. The direct manufacturing labor cost is $13.20 per hour.
bMachine costs include lease costs of the machine, repairs, and maintenance. Mammoth requires 8 machine-hours per unit and Maximum requires 4 machine-hours per unit. The machine hour rate is $19.80 per hour.
cManufacturing overhead costs are allocated to products based on machine-hours at the rate of $27.50 per hour.
Plum's controller, Steve Jacobs, is advocating the use of activity-based costing and activity-based management and has gathered the following information about the company's manufacturing overhead costs for the year ended November 30, 2013.
After completing his analysis, Jacobs shows the results to Charles Clark, the Plum division president. Clark does not like what he sees. "If you show headquarters this analysis, they are going to ask us to phase out the Maximum line, which we have just introduced. This whole costing stuff has been a major problem for us. First Mammoth was not profitable and now Maximum."
"Looking at the ABC analysis, I see two problems. First, we do many more activities than the ones you have listed. If you had included all activities, maybe your conclusions would be different. Second, you used number of setups and number of inspections as allocation bases. The numbers would be different had you used setup-hours and inspection-hours instead. I know that measurement problems precluded you from using these other cost-allocation bases, but I believe you ought to make some adjustments to our current numbers to compensate for these issues. I know you can do better. We can't afford to phase out either product."
Jacobs knows that his numbers are fairly accurate. As a quick check, he calculates the profitability of Maximum and Mammoth using more and different allocation bases. The set of activities and activity rates had used results in numbers that closely approximate those based on more detailed analyses. He is confident that headquarters, knowing that Maximum was introduced only recently, will not ask Plum to phase it out. He is also aware that a sizable portion of Clark's bonus is based on division revenues. Phasing out either product would adversely affect his bonus. Still, he feels some pressure from Clark to do something.
1. Using activity-based costing, calculate the gross margin per unit of the Maximum and Mammoth models.
2. Explain briefly why these numbers differ from the gross margin per unit of the Maximum and Mammoth models calculated using Plum's existing simple costing system.
3. Comment on Clark's concerns about the accuracy and limitations of ABC.
4. How might Plum find the ABC information helpful in managing its business?
5. What should Steve Jacobs do in response to Clark's comments?
Step by Step Answer: