Question:

PM Computers in Problem 44 is considering purchasing monitors from an American manufacturer that would guarantee a lead time of 8 days, instead of the Taiwanese company. Determine the new reorder point, given this lead time, and identify the factors that would enter into the decision to change manufacturers.