Product A has an MPS with 120 units to be produced in weeks 2 ,4, 5, 8,

Question:

Product A has an MPS with 120 units to be produced in weeks 2 ,4, 5, 8, 10, 11 and 13. The inventory information and structure is as follows:
Data category Lot sizing rule L4L FOQ=700 FOQ=700 L4L EOQ = 660 1 weeks 3 weeks 3 weeks Lead time 4 weeks 2 weeks Safety

The supplier of F has offered a reduced price if their order quantity is in multiples of 1000. The current price of F is $50 and holding cost is 1% of the value per week. Assuming this quarter is representative of a year, what much the price reduction break even point for us to be indifferent on the changed order quantity? Currently, each order placed costs $500.

Data category Lot sizing rule L4L FOQ=700 FOQ=700 L4L EOQ = 660 Lead time 3 weeks 3 weeks 4 weeks 2 weeks 1 weeks Safety
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Foundations of Operations Management

ISBN: 978-0132317535

3rd Canadian Edition

Authors: Larry P. Ritzman, Lee J. Krajewski, Manoj K. Malhotra, Robert D. Klassen

Question Posted: