Project Evaluation in the previous problem, suppose your required return on the project is 20 percent and
Question:
Project Evaluation in the previous problem, suppose your required return on the project is 20 percent and your pretax cost savings are $380,000 per year. Will you accept the project? What if the pretax cost savings are $280,000 per year? At what level of pretax cost savings would you be indifferent between accepting the project and not accepting it?