Refer to Cornerstone Exercise 7-29. The following activity data have been collected: Cutting .......$60,000 Assembling .....25,000 Inspecting

Question:

Refer to Cornerstone Exercise 7-29. The following activity data have been collected:

Cutting .......$60,000

Assembling .....25,000

Inspecting .......12,000

Reworking .....6,000


Required:

Calculate the activity rates that would be used to assign costs to each product.