Refer to the activity list given in Prob. 22.2-2 as Christine Phillips does more detailed planning for
Question:
(a) Find all the paths and path lengths through this project network. Which of these paths is a critical path?
(b) Find the earliest times, latest times, and slack for each activity. Use this information to determine which of the paths is a critical path.
(c) It is now one week later, and Christine is ahead of schedule. She has already selected a location for the sales meeting, and all the other activities are right on schedule. Will this shorten the length of the project? Why or why not?