Question: Refer to the data given in Exercise 21.21. In E21-21 Waikato City Council (WCC) is considering the purchase of a site for a new landfill.
Refer to the data given in Exercise 21.21.
In E21-21
Waikato City Council (WCC) is considering the purchase of a site for a new landfill. The purchase price for the site is $234000 and preparatory work will cost $88080. The landfill would be useable for 10 years. WCC hired a consultant, who estimated that the new landfill would cost $48000 per year less to operate than the current landfill. The current landfill will also last 10 more years. For a landfill project, WCC can borrow money from the government at a subsidized rate. WCC's required rate of return is only 6 per cent for this project. It does not pay any income taxes.
Required:
Calculate the internal rate of return for the landfill project. Should WCC approve the project?
Step by Step Solution
3.26 Rating (167 Votes )
There are 3 Steps involved in it
Acquisition cost of site time 0 234 000 Preparatory work t... View full answer