Question: Refer to the previous question. Morley Properties can hire a consultant to predict the most likely level of demand for this project. This consultant has

Refer to the previous question. Morley Properties can hire a consultant to predict the most likely level of demand for this project. This consultant has done many similar studies and has provided Morley Properties with the following joint probability table summarizing the accuracy of the results:



Refer to the previous question. Morley Properties can hire a


The sum of the entries on the main diagonal of this table indicates that the consultant’s forecast is correct about 82.25% of the time, overall.
a. Construct the conditional probability table showing the probabilities of the various actual demands given each of the forecasted demands.
b. What is the EMV of the optimal decision without the consultant’s assistance?
c. Construct a decision tree that Morley Properties would use to analyze the decision problem if the consultant is hired at a cost of $0.
d. What is the EMV of the optimal decision with the consultant’s free assistance?
e. What is the maximum price that Morley Properties should be willing to pay to theconsultant?

Actual Demand Medium 0.1600 0.0300 0.0100 0.2800 0.0225 0.0450 0.3825 High Forecasted Demand Low Medium High Low 0.0350 0.0350

Step by Step Solution

3.53 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Joint Probabilities Actual Demand Forecasted Demand Low Medium High Low 01600 00300 00100 Medium 0... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

167-B-M-L-M-D-A (483).xlsx

300 KBs Excel File

Students Have Also Explored These Related Management Leadership Questions!