Return to problem. Using OM Explorer, how long do you estimate the time required to install the

Question:

Return to problem. Using OM Explorer, how long do you estimate the time required to install the fifth pool?
A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate, without using the computer.
What is your estimate of the total time for all five pools?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra