Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past
Question:
Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a most likely completion time of 3 weeks, and a pessimistic completion time of 4 weeks. Activity B has estimated values of 5, 6, and 10 weeks for these three completion times. Similarly, activity C has estimated completion times of 1,1, and 4 weeks; and activity D has expected completion times of 8,9, and 13 weeks.
Phase 2 involves six separate activities. Activity E has activity A as an immediate predecessor. Time estimates are 1, 1, and 4 weeks. Activity F and activity G both have activity B as their immediate predecessor. For activity F, the time estimates are 3, 4, and 5 weeks. For activity G, the time estimates are 1, 3, and 5 weeks. The only immediate predecessor for activity H is activity C. All three time estimates for activity H are 5 weeks. Activity D must be performed before activity I and activity J can be started. Activity I has estimated completion times of 9, 10, and 11 weeks. Activity J has estimated completion times of 1,2, and 6 weeks.
Phase 3 is the most difficult and complex of the entire development project. It also consists of six separate activities. Activity K has time estimates of 2, 3, and 4 weeks. The immediate predecessor for this activity is activity E. The immediate predecessor for activity L is activity F. The time estimates for activity L are 3, 4, and 8 weeks. Activity M has 2, 2, and 5 weeks for the estimates of the optimistic, probable, and pessimistic times. The immediate predecessor for activity M is activity G. Activities N and O both have activity I as their immediate predecessor. Activity N has 8, 9, and 10 weeks for its three time estimates. Activity O has 1,1, and 4 weeks as its time estimates. Finally, activity P has time estimates of 4, 4, and 10 weeks. Activity J is the only immediate predecessor
Phase 4 involves five activities. Activity Q re-quires activity K to be completed before it can be started. All three time estimates for activity Q are 6 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 3 weeks. Activity S requires activity N to be completed first. Its time estimates are 6, 6, and 9 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3, 4, and 5 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1,2, and 3 weeks. Activity P must be completed before activity U can be started.
Phase 5 is the final phase of the development project. It consists of only two activities. Activity Y requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9,10, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started: activities S, T, and U. The estimated completion times for activity W are 2, 3, and 7 weeks.
(a) Given this information, determine the expected completion time for the entire process. Also determine which activities are along the critical path.
(b) Jim hopes that the total project will take less than 40 weeks. Is this likely to occur?
(c) Jim has just determined that activities D and I have already been completed and that they do not need to be part of the project. What is the impact of this change on the project completion time and the critical path?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managerial Decision Modeling With Spreadsheets
ISBN: 718
3rd Edition
Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair
Question Posted: