Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past

Question:

Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past two decades. Jim Sager, president of the firm, is considering the development of a new manufacturing line to allow it to produce high-quality plastic toys at reasonable prices. The development process is long and complex. Jim estimates that there are five phases involved and multiple activities for each phase.
Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a probable completion time of 3 weeks, and a pessimistic completion time of 4 weeks. Activity B has estimated completion times of 5, 6, and 8 weeks; these represent optimistic, probable, and pessimistic time estimates. Similarly, activity C has estimated completion times of 1 week, 1 week, and 2 weeks; and activity D has expected completion times of 8 weeks, 9 weeks, and 11 weeks.
Phase 2 involves six separate activities. Activity E has activity A as an immediate predecessor. Time estimates are 1 week, 1 week, and 4 weeks. Activity F and activity G both have activity B as their immediate predecessor. For activity F, the time estimates are 3 weeks, 3 weeks, and 4 weeks. For activity G, the time estimates are 1 week, 2 weeks, and 2 weeks. The only immediate predecessor for activity H is activity C. Time estimates for activity H are 5 weeks, 5 weeks, and 6 weeks. Activity D must be performed before activity I and activity J can be started. Activity I has estimated completion times of 9 weeks, 10 weeks, and 11 weeks. Activity J has estimated completion times of 1 week, 2 weeks, and 2 weeks.
Phase 3 is the most difficult and complex of the entire development project. It also consists of six separate activities. Activity K has three time estimates of 2 weeks, 2 weeks, and 3 weeks. The immediate predecessor for this activity is activity E. The immediate predecessor for activity L is activity F. The time estimates for activity L are 3 weeks, 4 weeks, and 6 weeks. Activity M has 2 weeks, 2 weeks, and 4 weeks for the estimates of the optimistic, probable and pessimistic time estimates. The immediate predecessor for activity M is activity G. Activities N and O both have activity I as their immediate predecessor. Activity N has 8 weeks, 9 weeks, and 11 weeks for its three time estimates. Activity O has 1 week, 1 week, and 3 weeks as its time estimates. Finally, activity P has time estimates of 4 weeks, 4 weeks, and 8 weeks. Activity J is its only immediate predecessor.
Phase 4 involves five activities. Activity Q requires activity K to be completed before it can be started. The three time estimates for activity Q are 6 weeks, 6 weeks, and 7 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 4 weeks. Activity S requires activity N to be completed first. Its time estimates are 6 weeks, 6 weeks, and 7 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3 weeks, 3 weeks, and 4 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1 week, 2 weeks, and 3 weeks. Activity P must be completed before activity U can be started.
Phase 5 is the final phase of the development project. It consists of only two activities. Activity V requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9 weeks, 10 weeks, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started. These are activities S, T, and U. The estimated completion times for activity W are 2 weeks, 4 weeks, and 5 weeks.
Given this information, determine the expected completion time for the entire process. Also determine those activities along the critical path. Jim hopes that the total project will take less than 40 weeks. Is this likely to occur?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 162

11th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: