Seasons Construction is constructing an office building under contract for Cannon Company. The contract calls for progress
Question:
Revenue______________________ Expenses
a. $3,750,000.........................$ 3,750,000
b. $14,880,000......................$15,000,000
c. $3,720,000........................$ 3,750,000
d. $3,720,000........................$ 4,200,000