Shen Construction Company had a long-term construction project that lasted three years. The project had a contract

Question:

Shen Construction Company had a long-term construction project that lasted three years. The project had a contract price of $150 million, with total estimated costs of $100 million. Shen used the percentage-of-completion method. At the end of construction, the following actual costs had been incurred:
_________________________________2012 2013 2014
Actual cost................................$25 million .........$55 million..............$20 million
Instructions
Calculate the revenue and gross profit that were recognized for each year of the construction contract.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Accounting Principles Part 3

ISBN: 978-1118306802

6th Canadian edition Volume 1

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Barbara Trenholm, Valerie Kinnear, Joan E. Barlow

Question Posted: