Shorts Company manufactures backpacks. A heavy-duty strap is one part that the company orders from an outside supplier. Information pertaining to the strap is as follows:
Economic order quantity...................................6,300 units
Average daily usage..........................................315 units
Maximum daily usage........................................375 units
Lead time..........................................................4 days
Required:
1. What is the reorder point assuming no safety stock is carried?
2. What is the reorder point assuming that safety stock is carried?