Skyline Corporation has decided to expand its operations and has purchased land in Salina for construction of
Question:
Land purchase price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $140,000
Payment of delinquent property taxes . . . . . . . . . . . . . . . . . . . . . 22,000
Title search and insurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7,000
City improvements for water and sewer . . . . . . . . . . . . . . . . . . . . 19,500
Building permit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 6,000
Cost to destroy existing building on land ($5,000 worth of salvaged material
used in new building) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24,000
Contract cost of new building . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,800,000
Land improvements—landscaping . . . . . . . . . . . . . . . . . . . . . . . . . 76,000
Sidewalks and parking lot . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41,000
Fire insurance on building—1 year . . . . . . . . . . . . . . . . . . . . . . . . . 20,000
The depreciated value of the old building on the books of the company from which the land was purchased was $29,000. The old building was never used by Skyline.
Instructions:
1. Determine the costs of the land and land improvements. Show clearly the elements included in the totals.
2. Determine the cost of the new building. Show clearly the elements included in the total.
Corporation
A Corporation is a legal form of business that is separate from its owner. In other words, a corporation is a business or organization formed by a group of people, and its right and liabilities separate from those of the individuals involved. It may...
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Intermediate Accounting
ISBN: 978-0324592375
17th Edition
Authors: James D. Stice, Earl K. Stice, Fred Skousen
Question Posted: