Question: Stanford Rosenberg Electronics wants to establish an assembly line for producing a new product, the Personal Little Assistant (PLA). The tasks, task times, and immediate
Stanford Rosenberg Electronics wants to establish an assembly line for producing a new product, the Personal Little Assistant (PLA). The tasks, task times, and immediate predecessors for the tasks are as follows:
.png)
Rosenberg’s goal is to produce 180 PLAs per hour.
(a) What is the cycle time?
(b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?
(c) Can the theoretical minimum actually be reached when workstation areassigned?
Time (sec) 12 15 Immediate Predecessors Task B, C 20