Sweatshop has the following details of direct labour used to make tracksuits for July.
(a) Standard: 550 sweatshirts at 2 hours at £3.50 per hour.
(b) Actual production: 500 sweatshirts at 1,050 hours for £3,780.
Required: LO1 Calculate the:
(i) overall direct labour cost variance
(ii) direct labour price variance
(iii) direct labour quantity variance.