Sweatshop has the following details of direct labour used to make tracksuits for July. (a) Standard: 550

Question:

Sweatshop has the following details of direct labour used to make tracksuits for July.

(a) Standard: 550 sweatshirts at 2 hours at £3.50 per hour.

(b) Actual production: 500 sweatshirts at 1,050 hours for £3,780.

Required: LO1 Calculate the:

(i) overall direct labour cost variance

(ii) direct labour price variance

(iii) direct labour quantity variance.