11. A business is evaluating a project that is more risky than its core business. The appropriate...
Question:
11. A business is evaluating a project that is more risky than its core business. The appropriate discount rate should be?
& Lower than the normal cost of capital
& Higher than the normal cost of capital
& The normal cost of capital
& The rate of interest paid on its overdraft
& The rate of interest earned on cash deposited in a bank