The following information relates to Osprey Limited: Budgeted production: 500 units. Standard hours per unit: 10. Actual
Question:
The following information relates to Osprey Limited:
Budgeted production: 500 units.
Standard hours per unit: 10.
Actual production: 600 units.
Budgeted fixed overhead: £125 000.
Actual fixed overhead: £120 000.
Actual hours worked: 4900.
Required:
Calculate the following fixed production overhead variances:
1 total;
2 expenditure;
3 volume;
4 capacity; and 5 efficiency.