Using the data from the previous question, calculate the following performance measures: Data from previous question The

Question:

Using the data from the previous question, calculate the following performance measures:

Data from previous question

The following information relates to Osprey Limited:

Budgeted production: 500 units.

Standard hours per unit: 10.

Actual production: 600 units.

Budgeted fixed overhead: £125,000.

Actual fixed overhead: £120,000.

Actual hours worked: 4900. 


(a) Efficiency ratio
(b) Capacity ratio
(c) Production volume ratio.