The program evaluation and review technique (PERT) is widely used to plan and measure progress toward scheduled
Question:
The program evaluation and review technique (PERT) is widely used to plan and measure progress toward scheduled events. PERT is combined with cost data to produce a PERT- cost analysis to
a. calculate the total project cost inclusive of the additional slack time.
b. evaluate and optimize trade-offs between time of an event's completion and its cost to complete.
c. implement computer-integrated manufacturing concepts.
d. avoid the problem of time variance analysis.
e. calculate expected activity times.