Consider this network diagram below, in which the duration of each activity is given in weeks. Calculate

Question:

Consider this network diagram below, in which the duration of each activity is given in weeks.

Calculate the critical path and the total duration of the project.

1 7

4 9

8 2

7 3

5 2

2 11 3

12 6

10 Start Finish

 LO.1