Four products (A-D) are made in a batch processing plant. The times (in hours) required for each
Question:
Four products (A-D) are made in a batch processing plant. The times (in hours) required for each piece of equipment for each product are shown in Table P3.15.
Using the information in Table P3.15, answer the following questions:
- Is this a jobshop or flowshop plant?
- Over a 600 h period (approximately 1 month), the required number of batches for products B and D is 25 and 10, respectively.
- The demand for products A and C is such that twice as many batches of A compared to C are required. Determine how many batches of A can be manufactured if single product campaigns are used. In your calculations, you should use the exact cycle time expression for each product.
- Repeat Part (b) but use the limiting cycle time for each product.
- For a process with unlimited intermediate storage (uis process) and an equal number of batches for each product, determine the maximum number of batches for each product using a mixed product campaign (ABCDABCD… or ACBDACBD…, etc.) in a 600 h operating period.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Analysis Synthesis And Design Of Chemical Processes
ISBN: 9780134177403
5th Edition
Authors: Richard Turton, Joseph Shaeiwitz, Debangsu Bhattacharyya, Wallace Whiting
Question Posted: